Facility name: Medical City McKinney
Project name: MCMKNY-102017M-BH & Rehab Relocation
Location: MCKINNEY, TX
Project classification: Hospital – Horizontal Expansion
Project type: Psych
Project number: 3833300011
Lesson Learned number: 145
Impact: Schedule, Quality, Safety
Location: MCKINNEY, TX
Project classification: Hospital – Horizontal Expansion
Project type: Psych
Project number: 3833300011
Lesson Learned number: 145
Impact: Schedule, Quality, Safety
Lesson Learned/Best Practice
Utilization of extensive utility exploration limited any interruptions due to interferences with existing underground utilities, utilized extensive hydro-vac excavation, survey was coordinated into BIM, early mobilization in anticipation of city permit. Was able to accomplish a lot of the actions because was an EDI project.
Suggested Actions for Future Projects
As possible integrate as many of the same methods for future projects. Key is early mobilization to be able to take advantage of any mobilization or relocation due to unforeseen utilities identified.
Keywords
Pre construction site survey