Facility name: Menorah Medical Center
Project name: MENORA-092018M-Bed Tower Expansion
Location: OVERLAND PARK, KS
Project classification: Hospital – Horizontal Expansion
Project type: Acute Care
Project number: 0972300007
Lesson Learned number: 115
Impact: Cost, Schedule, Quality
Location: OVERLAND PARK, KS
Project classification: Hospital – Horizontal Expansion
Project type: Acute Care
Project number: 0972300007
Lesson Learned number: 115
Impact: Cost, Schedule, Quality
Lesson Learned/Best Practice
Early understanding of local code requirements for the transformer and switchgear pads is important as this could impact the release of prefabricated duct banks. If the equipment pad sizes and locations are not correctly identified this could cause rework of prefabricated material.
Suggested Actions for Future Projects
Coordinate early with the local utility company and design team in order to correctly identify the transformer and switchgear pad requirements and location.