Facility name: North Florida Regional Medical Center
Project name: NRFLMC-032018M-South Tower Vertical Expansion
Location: GAINESVILLE, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3091600012
Lesson Learned number: 97
Impact: Cost, Schedule
Location: GAINESVILLE, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3091600012
Lesson Learned number: 97
Impact: Cost, Schedule
Cost impact: $9,000
Lesson Learned/Best Practice
On a vertical expansion job there is a need to jump exhaust fans from existing roof to the new roof before the final roofing has been installed, therefore temporary lightening projection needed to be coordinated in advance.
Suggested Actions for Future Projects
As part of preconstruction/MOP note the need for protection in order to coordinate necessary trades.
Keywords
coordination, lightening, temporary, MOP, preconstruction, fan, exhaust, roof top, safety, dry-in