Facility name: Orange Park Medical Center
Project name: ORPKMC-092018M-Bed Tower
Location: ORANGE PARK, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3091300035
Lesson Learned number: 48
Impact: Schedule
Location: ORANGE PARK, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3091300035
Lesson Learned number: 48
Impact: Schedule
Lesson Learned/Best Practice
Current steel installation schedule activities often combine tasks for install and subsequently have multiple crews listed under on activity. An example of this would be Steel Detailing which consists of multiple tasks such as decking, moment welds, bent plate, and welding studs. It is imperative, especially on jobs with LPS, to have crew specific tasks and duration.
Suggested Actions for Future Projects
During pre-construction meeting, review the process the installer is planning and divide activities by major task and labor load accordingly.