Special Considerations when using victaulic fittings

Facility name: Memorial Health UMC Savannah

Project name: MEMSAV-092018M-3rd and 4th Floor Shell Buildout
Location: SAVANNAH, GA
Project classification: Hospital – Shell Buildout
Project type: Acute Care
Project number: 2696000011
Lesson Learned number: 54
Impact: Cost, Schedule, Quality, Scope


Lesson Learned/Best Practice

When bidding the project, if the specifications include Victaulic Grooved Couplings & Fittings, engage the HCA Construction Manager and design team on accepted locations of use.  There are specific locations within existing & new buildings where this product can be used.  As a rule of thumb open mechanical rooms are acceptable, but only if not located above patient care areas. We believe it is best to handle on a case by case basis.


Suggested Actions for Future Projects

Make decisions in early planning stages to include all players, providing accurate pricing & schedule implications.  Begin early conversations with HCA team members and design.


Actions Taken / Current Status

Use of Victaulic fittings is addressed in the HCA MEP Guidelines, Section 23 20 00:  HVAC Piping.  See attached file for this section of the guidelines.