Site Visits on Renovation Projects

Facility name: Medical Equipment Lessons Learned

Project name: Medical Equipment Lessons Learned
Location: ,
Project classification:
Project type: Other
Project number: 0000000000
Lesson Learned number: 7
Impact: Cost


Lesson Learned/Best Practice

Any project that includes a renovation component, the AVP of MEM will review scope of the project with ME Manager to determine if an onsite visit to review proejct details and assess existing medical equipment would be beneficial.


Suggested Actions for Future Projects

When planning books are issued ME Manager would visit with AVP to discuss project scope and whether an onsite visit and assessment of existing equipment should be done prior to submitting a budget.