Lesson Learned number: 16
Impact: Schedule
Location: ,
Project classification:
Project type: Other
Project number: 0000000000
Lesson Learned number: 16
Impact: Schedule
Lesson Learned/Best Practice
ME Manager will schedule a site readiness walk for each project to determine if the site is ready to accept equipment delivery.
Suggested Actions for Future Projects
ME Manager with coordinate with the contractor to schedule a site visit on each project to determine if site is ready to accept equipment.