Facility name: Aventura Hospital & Medical Center
Project name: AVENTU-New Tower
Location: AVENTURA, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3092000015
Lesson Learned number: 139
Impact: Quality, Safety, Scope
Location: AVENTURA, FL
Project classification: Hospital – Vertical Expansion
Project type: Acute Care
Project number: 3092000015
Lesson Learned number: 139
Impact: Quality, Safety, Scope
Lesson Learned/Best Practice
Ensuring that all existing utilities are up and fully functioning after shutdown is complete
Suggested Actions for Future Projects
Add line items on MOP form/paperwork for facility approval and completion of work. Prior to the shutdown occurring walk existing space with facility management personnel and have form signed at the beginning of the shutdown. After the work is complete and GC/sub believe the hospital should be back up and running re-walk all spaces with facility management personnel to confirm and have them sign off on the form saying they have walked and verified that the work is complete