Lesson Learned/Best Practice

Ensuring that all existing utilities are up and fully functioning after shutdown is complete


Suggested Actions for Future Projects

Add line items on MOP form/paperwork for facility approval and completion of work. Prior to the shutdown occurring walk existing space with facility management personnel and have form signed at the beginning of the shutdown. After the work is complete and GC/sub believe the hospital should be back up and running re-walk all spaces with facility management personnel to confirm and have them sign off on the form saying they have walked and verified that the work is complete