OFE Schedule

Facility name: North Austin Medical Center

Project name: NRTAUS-022019M-Rehab/Peds Relocation
Location: AUSTIN, TX
Project classification:
Project type: Acute Care
Project number: 0822400025
Lesson Learned number: 127
Impact: Schedule


Lesson Learned/Best Practice

Keep lead time for OFE items in mind when planning projects. Typical 120 day lead time should be considered during initial planning phase. Notification to equipment vendors needs improvement for coordination with construction schedule. 


Suggested Actions for Future Projects

Notification of construction kickoff to equipment vendors needs improvement for coordination of long lead time items with construction schedule. Include OFE vendors in initial schedule development.


Keywords

owner furnished, equipment