Medical Equipment Data Requirements

Facility name: UCF Lake Nona Medical Center

Project name: Lake Nona-102018M- New Hospital
Location: TALLAHASSEE, FL
Project classification: Hospital – New
Project type: Acute Care
Project number: 2689500001
Lesson Learned number: 118
Impact: Cost


Lesson Learned/Best Practice

Imaging equipment vendors require live data drops immediately following mechanical installation to test and calibrate equipment.


Suggested Actions for Future Projects

Low voltage subcontractor should carry cost to patch in data drops for imaging equipment prior to all other drops.


Keywords

Medical Equipment, Data, Imaging