Lesson Learned/Best Practice

Begin design coordination of Hybrid rooms where multiple vendors are involved earlier in the process during SD 


Suggested Actions for Future Projects

Need to identify all vendors prior to schematic design and have detailed coordination lead by ME Manager with Design team, facility and vendors