Facility name: Medical Equipment Lessons Learned
Project name: Medical Equipment Lessons Learned
Location: ,
Project classification:
Project type: Other
Project number: 0000000000
Lesson Learned number: 9
Impact: Quality, Scope
Location: ,
Project classification:
Project type: Other
Project number: 0000000000
Lesson Learned number: 9
Impact: Quality, Scope
Lesson Learned/Best Practice
Begin design coordination of Hybrid rooms where multiple vendors are involved earlier in the process during SD
Suggested Actions for Future Projects
Need to identify all vendors prior to schematic design and have detailed coordination lead by ME Manager with Design team, facility and vendors