Facility name: P-SL Medical Center
Project name: PRSTLK-022017P1-Surgery Renovation
Location: DENVER, CO
Project classification: Hospital – Renovation
Project type: Acute Care
Project number: 2720000020
Lesson Learned number: 88
Impact: Quality
Location: DENVER, CO
Project classification: Hospital – Renovation
Project type: Acute Care
Project number: 2720000020
Lesson Learned number: 88
Impact: Quality
Lesson Learned/Best Practice
On past shutdowns at the facility, not everyone was clear on who was responsible for shutting systems down and exactly how to shutdown systems so that only the areas where the work is taking place was affected. Walk all MOP/Shutdown’s with the facility.
Suggested Actions for Future Projects
All MOP’s/Shutdowns moving forward should be walked with all parties involved so that everyone is clear on responsibilities and what is required for the shutdown. MOP’s will also be submitted and walked well in advance so that there is enough time for the information to be passed along to necessary personnel.
Keywords
shutdowns, MOP, EDI, utility, phasing