Coordination of project plans with facility low voltage system vendors

Facility name: Rose Medical Center

Project name: ROSEMC-032018M-Women’s Center Renovations
Location: DENVER, CO
Project classification: Hospital – Renovation
Project type: Acute Care
Project number: 2730000012
Lesson Learned number: 90
Impact: Cost, Schedule


Lesson Learned/Best Practice

There should be early front-end coordination with Vendors and Elect/LV trade partners.  With the “minor renovation” scopes, identifying all low-voltage systems and who is responsible can be challenging and lack of early front-end coordination can impact schedule and costs when bringing systems back online.


Suggested Actions for Future Projects

Existing equipment coordination would need to be managed between the GC and the facility DFM/ Director of IT&S.  Sugguested action would be a site walk of the area being renovated with the GC PM/Super and the Facility DFM/ITS Director.


Keywords

coordination, low voltage, rework, demo, renovation, medical equipment