City of Orlando – Signage Permitting

Facility name: UCF Lake Nona Medical Center

Project name: Lake Nona-102018M- New Hospital
Location: TALLAHASSEE, FL
Project classification: Hospital – New
Project type: Acute Care
Project number: 2689500001
Lesson Learned number: 119
Impact: Schedule

Schedule impact: 60 days


Lesson Learned/Best Practice

The City of Orlando permitting process for exterior signage is a minimum of 60 days often resulting in delays to signage installation.


Suggested Actions for Future Projects

A permit expediter should be utilized for any signage permits in the City of Orlando.


Keywords

City of Orlando, Signage