Facility name: UCF Lake Nona Medical Center
Project name: Lake Nona-102018M- New Hospital
Location: TALLAHASSEE, FL
Project classification: Hospital – New
Project type: Acute Care
Project number: 2689500001
Lesson Learned number: 135
Impact: Cost
Location: TALLAHASSEE, FL
Project classification: Hospital – New
Project type: Acute Care
Project number: 2689500001
Lesson Learned number: 135
Impact: Cost
Lesson Learned/Best Practice
BLOX Patient Bathroom lights are fed from critical branch power, per HCA & ICT guidelines, and are fabricated with flex conduit connections. The City of Orlando requires that all critical branch power be ran in rigid conduit
Suggested Actions for Future Projects
If a BLOX design alteration for the City of Orlando is not feasible, the contractor should carry cost to remove flex conduit and install rigid pipe in the City of Orlando.
Keywords