Medical Equipment – Delivery / Installation

AHCA – Medical Equipment Drawings

Facility name: UCF Lake Nona Medical Center

Project name: Lake Nona-102018M- New Hospital
Location: TALLAHASSEE, FL
Project classification: Hospital – New
Project type: Acute Care
Project number: 2689500001
Lesson Learned number: 150
Impact: Cost


Lesson Learned/Best Practice

AHCA requirements for Imaging equipment varies with each “team”. Typically, the specific details required by AHCA are not included in the site specific vendor drawings resulting in added scope and rework during the inspection process.


Suggested Actions for Future Projects

Medical Equipment vendors should incorporate known AHCA requirements for each specific team in the vendor documents for the project. 


Keywords

Medical Equipment, AHCA

Need better facilities move in coordination

Facility name: Medical City McKinney

Project name: MCMKNY-102017M-BH & Rehab Relocation
Location: MCKINNEY, TX
Project classification: Hospital – Horizontal Expansion
Project type: Psych
Project number: 3833300011
Lesson Learned number: 149
Impact: Schedule


Lesson Learned/Best Practice

Needed to have conducted a more comprehensive equipment/material move in plan/review


Suggested Actions for Future Projects

Conduct with construction and facility teams move in pull plan to go over all actions associated with equipment/material/personnel move in.


Keywords

Move in, equipment/materal delivery, pull plan

Equipment Vendor Communication

Facility name: Los Robles Hospital And Medical Center

Project name: LOSROB-042017P2-Imaging Relocation
Location: THOUSAND OAKS, CA
Project classification: Hospital – Horizontal Expansion
Project type: Acute Care
Project number: 3055500036
Lesson Learned number: 66
Impact: Cost


Lesson Learned/Best Practice

Lesson learned here is to create a monthly dialogue with HCA’s Medical Equipment vendors who deliver equipment to the project toward completion.

We found a best practice to be creating somewhat of a “monthly newsletter” that goes out to the vendors with site updates, schedule updates, and progress of the project. This helps create a better dialogue with vendors so they know who they are dealing with and who to ask questions and follow up with. This also creates a streamline service so no delivery is showing up late or early. This will be applied to our projects moving forward.


Suggested Actions for Future Projects

Create a monthly newsletter to equipment vendors with site updates, schedule updates, and progress of the project to improve dialogue with vendors and ensure no delivery shows up too late or early.


Actions Taken / Current Status

A monthly vendor newsletter may be useful on some projects and should be considered when appropriate.  Additionally, for all projects, there should be Medical Equipment vendor coordination calls (separate from OAC meetings) starting 120 days prior to the occupancy date.

Site Readiness Visits

Facility name: Medical Equipment Lessons Learned

Project name: Medical Equipment Lessons Learned
Location: ,
Project classification:
Project type: Other
Project number: 0000000000
Lesson Learned number: 16
Impact: Schedule


Lesson Learned/Best Practice

ME Manager will schedule a site readiness walk for each project to determine if the site is ready to accept equipment delivery.


Suggested Actions for Future Projects

ME Manager with coordinate with the contractor to schedule a site visit on each project to determine if site is ready to accept equipment.